South African PV projects mitigate land rights risks amid strong growth | Land Portal

By: Heba Hashem
Date: March 2nd 2016
Source: PV Insider

International developers must include potential local land claims in project risk profiles and prepare for a new South African law which is set to ban new freehold land ownership by foreign entities.

In support of black empowerment, South Africa reopened its land claim process in June 2014 after closing it at the end of 1998, giving land claimants another five years to lodge claims. Any person or community dispossessed of land rights after 19 June 1913 as a result of racially discriminatory practices are able to lodge a claim to restore such a right or receive compensation by 30 June 2019.

The land claims process has raised the importance of careful research and legal preparation during the development phase of renewable energy projects, as South Africa moves forward with its Renewable Energy Independent Power Producer Procurement Programme (REIPPPP). The South African government has set a target of 8.4 GW of solar PV capacity by 2030 and so far 2.3 GW has been procured.

“What’s different here from Europe is that you have the black economic empowerment program,” said Matteo Brambilla, managing director for Africa at Building Energy.

The Italian company developed the 81 MW Kathu PV plant in Northern Cape, which became operational in August 2014, and has more than 20 renewable energy projects in the country at different stages of development.

A new law due to be presented to South Africa's Cabinet in the first half of 2016 is also set to impact future land acquisition decisions. The Regulation of Land Holdings Bill would prohibit foreigners from owning land freehold, and instead allow them to lease plots for periods between 30 and 50 years.

The proposed policy was first announced by President Jacob Zuma in early 2015 and will not apply to those who have already acquired the freehold.

"It is recognised that this cannot apply retrospectively without constitutional infringements," the South African Government News Agency said in a statement February 11.

"As such those who have already acquired freehold would not have their tenure changed by the passing of the proposed law," it said.

Land claims

To date, successful developers in South Africa’s Renewable Energy Independent Power Producer Programme (REIPPP) have either secured their projects’ land rights through a long-term lease, usually up to 25 years, or through the transfer of title (freehold acquisition), according to law firm Hogan Lovells.

Building Energy reached financial close on the Kathu PV project in November 2012, one year after it was awarded. A total of $360 million was invested in the plant and it is delivering above 20% in annual return on investment, Brambilla said. There is "plenty of room" for further development under South Africa's REIPPPP, he said.

“For Kathu, we bought the land. There are no limitations on land transactions; the only difficulty is that there might be land claims in some parts of the country,” Brambilla said.

According to South African law firm Wersmans Attorneys, eastern provinces such as Mpumalanga and Limpopo have seen some of the largest demand from renewable energy suppliers and these are also the two areas where the most land claims have been lodged.

Building Energy's Mkuze bioenergy plant in KwaZulu-Natal province, eastern South Africa, faced land claims in 2015. The developer has tackled these issues and aims to start up the plant by mid-2017.

“Land claims are historically granted to disadvantaged people who may at some point claim ownership of their land, so this is something that may happen. In Kathu [PV project in Northern Cape], we didn’t have issues but in other projects we had to deal with such issues and we used consultants and lawyers,” said Brambilla.

In the case of the Mkuze bioenergy plant, claims were lodged by four communities bordering the 3,500-hectare project site.

“Land owners’ rights can be complex, especially when multiple parties can claim ownership,” David Cunningham, cleantech and renewables analyst at global consultancy SgurrEnergy, said.

“This can cause difficulties when trying to define the beneficiary community and when designing the community benefit structures to which revenue will be channelled,” he said.

Best practice

According to Werksmans Attorneys, project investors should notify the Land Claims Commission of intended projects on any and all land, as some claims may have been submitted but are not published in official documentation.

“The fact that a claim has not been published does mean it does not exist.” Bulelwa Mabasa, director at Werksmans Attorneys and an expert in land restitution law, said in a statement.

Developers should take comfort in the fact that even if a land claim is found to be valid, the state can offer to purchase the land from the landowner on the basis of fair and just compensation, Mabasa said.

Brambilla noted that land claims are normally assigned to a commissioner who decides what to do with the land and whether the claim has any grounds. If there are grounds, the commissioner determines the right price to pay for the owner.

“Usually, the government itself pays the price on behalf of the person who is claiming that piece of land. I must say that South Africa has a good regulatory framework that is quite developed, simple and friendly," he said.

The Land Claims Commission has successfully facilitated agreements among project funders, landowners and land claimant communities and expropriation of land is highly unlikely, Werksmans Attorneys said.

“Renewable energy is in effect foreign direct investment and the [Lands Claims] Commission has, in most cases, been cooperative and forthcoming in support of renewable energy projects,” Mabasa said.

Faster progress

The earlier rounds of the REIPPPP typically required interested bidders to show that their projects were at an advanced stage of development by securing land rights to the project site, whether via ownership or leases.

An expedited bid window in the latest round launched in June 2015 simplified the process and required bidders to explain in writing any restrictive conditions in the title deeds of their sites and how they intended to resolve them.

Developers will need to allocate sufficient resources for any potential land claims and understand the implications of the forthcoming legislation on freehold land ownership.

“Perseverance is key when dealing with land owners and government departments,” Terence Govender, SolarReserve’s vice president of development for Africa, told PV Insider.

SolarReserve's Lesedi, Letsatsi and Jasper PV plants provide a total of 246 MW of power to the South African grid.

“It is also important for a foreign solar developer to have a team with deep experience in developing energy projects internationally, and ideally in Africa,” Govender said.

--

Read original article here

Photo source:  Steve Slate via Flickr/Creative Commons (CC By-NC-ND 2.0). Photo: © Steve Slater

Copyright © Source (mentioned above). All rights reserved. The Land Portal distributes materials without the copyright owner’s permission based on the “fair use” doctrine of copyright, meaning that we post news articles for non-commercial, informative purposes. If you are the owner of the article or report and would like it to be removed, please contact us at hello@landportal.info and we will remove the posting immediately.

Various news items related to land governance are posted on the Land Portal every day by the Land Portal users, from various sources, such as news organizations and other institutions and individuals, representing a diversity of positions on every topic. The copyright lies with the source of the article; the Land Portal Foundation does not have the legal right to edit or correct the article, nor does the Foundation endorse its content. To make corrections or ask for permission to republish or other authorized use of this material, please contact the copyright holder.